




WHAT THE CLIENT SAID
“Having worked with Teepee on several previous occasions, they were our first choice supplier when it came to the installation of additional mezzanine floors. As ever, their service was cost-effective, efficient and proactive, enabling us to continue working with minimal impact to our production schedule. Well done to the Teepee team on another excellent delivery.”
– Production Director
CHALLENGES
The project required a quick turnaround with little or no impact on productivity. Once delivered to site, Teepee agreed on an installation program to ensure there was minimal disruption to the client’s business.
HOW WE SUCCEEDED
During the tender stage, a concept drawing of the mezzanine floors was provided, for which Building Regulations approval had been verbally obtained.
On receipt of the order, Teepee carried out a detailed site survey to enable the floor design to be completed. On approval, the mezzanine floor was issued for manufacturing and structural calculations were sent to our building inspector for formal approval.
Before arrival onsite, Teepee issued relevant method statements and risk assessments following CDM regulations, which also included submission of a detailed installation plan.
Once the mezzanine floor was erected, Teepee installed partitions, shelving and mechanical and electrical services (M&E). On completion of all works, the building inspector carried out his final onsite inspection, before final certificates being issued to the client.
OUR SOLUTION PROVIDED
- Additional 7,757 sq ft (721m2) of storage space.
- Space below provided canteen, secure stores and production areas.
- All floors fitted with safety gates to load palletised goods.
- Building regulations approval obtained on client’s behalf.
Share this Case Study: