George Taylor & Co Lifting Gear (Midlands) Ltd

WHAT THE CLIENT SAID

“In an industry such as ours, Health & Safety considerations are of paramount importance and our chosen supplier needed to take this element very seriously. As a SEMA approved supplier, we knew that Teepee’s work would comply with the very latest industry and HSE standards which when combined with their professional and thorough approach, inspired great confidence in their handling of the project. In particular, we were impressed by the level of detail applied to the calculation of racking point loads and the care taken to ensure not only compliance but also optimal safety. The team were a pleasure to work with and we would not hesitate to recommend them to others”
– Managing Director

 

CHALLENGES

The new facility consisted of a mezzanine floor with offices above and below, along with a first aid room and rest area facility located on the ground floor.

Before the relocation of the warehouse, GT Lifting required a dispatch warehouse to store a combination of handpicked goods, timber pallets and stillages.

Once completed, part of the existing racking could be re-located to create a new ‘bulk storage’ warehouse.

HOW WE SUCCEEDED

Firstly Teepee designed a new dispatch warehouse facility comprising of a new adjustable pallet racking system fitted with open boarded timber decking throughout, to enable a total of 5 different size timber pallets and steel stillages to be stored.

When storing goods of this nature, racking bay loads would exceed 15000 Kgs per bay, which generally surpasses standard concrete floor slab point loads. To overcome this issue, Teepee carried out floor slab tests to establish the strength of the concrete slab. On reviewing the results, Teepee installed spreader plates underneath all uprights, as this proved a more cost-effective solution than reinforcing the concrete slab. After the installation was finalised, GT Lifting began to migrate stock over from their existing warehouse.

After completion of the racking, Teepee designed and installed a mezzanine floor. This design consisted of offices on both levels, enabling necessary departments to be in direct contact with operational staff. Additional features included a tea point facility on the first floor and a first aid room with general rest area located on the ground floor.

Once the new racking had been filled, Teepee were able to dismantle and re-locate existing racking to create a ‘bulk storage’ warehouse. While installing the existing racking, all damaged components were replaced, then on completion, all racks were commissioned and fitted with new load notice signs.

During the fit-out, Teepee co-ordinated with client’s chosen electrical, mechanical and building contractors.

 

OUR SOLUTION PROVIDED

  • A combination of 2113 No. pallet/stillage locations was created, accessible by both articulated and counterbalance forklifts.
  • Two storey office facilities fitted with suitable amenities.
  • Existing racking re-sited and commissioned to SEMA standards.
  • Pedestrian and end of aisle racking barriers fitted throughout, to comply with HSE / SEMA recommendations.
  • All works designed and installed to obtain Building Regulation approval.

 

Share this Case Study: